Appendix 1 – Revenues & Benefits Workflow/ EDM Replacement Project Costs
|
||
|
2023/24 |
2024/25 |
|
|
Staffing costs |
Staff
costs |
Staff
costs |
|
Project/Service staff |
£ 313,317.66 |
£ 181,511.02 |
|
IT&D recharges |
£ 69,322.63 |
£ 27,333.63 |
|
Consultancy |
£ 45,000.00 |
£ 20,000.00 |
|
Total staff costs |
£ 427,640.30 |
£ 228,844.65 |
|
Indicative Supplier Project costs |
2023/24 |
2024/25 |
|
Project costs, Data load, Implementation, Training & Discovery Work |
£ 43,175.00 |
|
|
Indicative data extraction/migration costs |
2023/24 |
2024/25 |
|
Document transfer, data extract, robotic processes, archiving |
£ 50,000.00 |
£ 50,000.00 |
|
2023/24 |
2024/25 |
|
|
|
|
|
|
Total project cost per year |
£ 520,815.30 |
£ 278,844.65 |
|
Overall projected cost |
|
£ 799,659.95 |
|
|
|
|
|
|
|
|